Wednesday, 30 November 2011

DMRC project target fixed for completion of each route

Delhi Metro Rail
Delhi Metro Rail Corporation Limited (DMRC) has informed that the following metro lines/sections have been commissioned in Delhi in 2011:-
S.No.
Corridor/Section
Length (km.)
Number of Stations
Commissioning Date
1.
Sarita Vihar - Badarpur

4.82
3
14.01.2011
2.
High Speed Airport Metro Express Link from New Delhi Railway Station –IGI Airport- Dwarka Sector-21
22.70
6
23.02.2011
3.
Kirti Nagar - Ashok  Park Link

3.31
2
27.08.2011

This was stated by the Minister of State for Urban Development, Shri Saugata Roy in a written reply in Lok Sabha today.  He further state that the details of ongoing metro lines alongwith the funds allocated and spent by DMRC for the project, as well as the target fixed for completion of each route, are given below:-

S.
No.
Route name
Total (km.)
Stations
Target fixed for completion
Funds allocated in 2011-12
(Rs. in crore)
Funds spent by  DMRC
(Rs. in crore)

Delhi Metro Phase III







700.89







29.83
1.
Mukundpur to Yamuna Vihar
55.697
35
March, 2016
2.
Janakpuri West to Kalindikunj
33.494
22
February, 2016
3.
Central Secretariat to Kashmere Gate
9.37
7
December, 2016
4.
Jahangirpuri to Badli Corridor
4.489
3
December, 2014

Total
103.050
67


5.
Extension from Badarpur to Faridabad
13.875
9
September, 2014
100
0.04
                       
                        Expansion of metro services is an ongoing process with reference to urbanization. Delhi Metro network is planned to be executed in four phases.  The Phase-I comprising of 65.10 km. and Phase-II comprising of 124.93 km.  are   already  operational.  The Government of India has also sanctioned the implementation of Delhi Metro Phase- III of length 103.05 km. indicated above. DMRC has also been directed to initiate the survey work of Delhi Metro Phase-I

No comments:

Post a Comment